Letter to Lorain Civil Service Commission Pt.2

Continued: Click on the jpgs to  enlarge

Max Upton and Mayor Jack Bradley

Part One : https://oheragain.wordpress.com/2021/11/29/letter-to-the-civil-service-commission-part-1/

The continuing story of St. Joseph’s Demolition

 

Acting Director of Building and Planning Max Upton St.    Joseph’s Hospital demolition

 

Unfortunately, for Lorain and my deepening concern as to the capabilities of Mr. Upton we now come to   the demolition of St. Joes Community Center, the old St. Joseph’s Hospital.

 

I would ask you  to  remember the City  of Lorain  and this edifice that was  and  has been a bone of contention since 1997  when South  Shore Development took over the building with  Federal monies.

 

  “South Shore took ownership of the St. Joseph facility in 1997 after St. Joseph Hospital merged with Lorain Community Hospital to create Community Health Partners. An $800,000 federal grant was used to get the building ready for its new tenants. Additional grants and loans were secured. The state had $1.4 million in loans invested in the community center, while the county and the city each have $700,000 in loans tied to the center”.

75_4-11-16commmin%20(1)%20(2).pdf

 I  would also   ask you  to  remember  the history  of how  the hospital originally came into  being  due to  the Devonian Sulphur Springs that  are still bubbling away  underneath  that acreage

Lorain in Retrospect- JJ Meyers

was erected a large three story frame building designed as a sanitarium, in which with the liberal internal and external application of certain water oozing from a nearby spring, a cure for numberless ailments was proclaimed by the promoters.

The house was called the “Devonian Baths” and was built in 1887 over Sulphur springs discovered by accident by Gilbert Hogan, who had been drilling for natural gas. 

 

Please Note once again the dates are very important in the following thoughts and documentation provided.

 

Time line begins in this instance on March 23rd 2020 and the reporting in the Chronicle Telegram of the sale of  the property.

 Mar 23, 2020 9:28 PM

Former St. Joseph Community Hospital complex sold for $150,000 | Chronicle Telegram

LORAIN — the defunct St. Joseph Community Center has sold.

South Shore Development Corp. LLC — whose sole remaining member is Jim Janasko of Janasko Insurance — finalized a deal with A7 Development Group LLC out of Massachusetts.

The 24-parcel property sold for $150,000, effective March 16. The Lorain County Auditor’s website lists the total assessed value of all parcels combined as at about $1.3 million.

 

I am still trying to confirm through various means just who it was that introduced A7 to Lorain.

 Time line: St Joes.

March 23   2020  

 SOLD TO A7 Development Group LLC (with outstanding taxes, and utilities) 

 A7 Development Corp LLC by March 

2020 had been in business for a little over 2 years and has one principle Salvatore Tecce A7 Development Company   File No. 001 348859

Registered Address: 4 DENSEREAUX PLACE, MIDDLETON 01949 MA

SALVATORE TECCE (who is the company’s only principle. He is the agent, president, vice president, director, treasurer and secretary

Salvatore Tecce is also one of the two “principles for the   demolition company   hired by A7 Development (Group) Corp –“Earth Exchange” And please note the date of their registration.

EARTH EXCHANGE INC. has been set up 2/16/2021 in state MA. The current status of the business is Active. The EARTH EXCHANGE INC. principal address is 800 TURNPIKE ST STE 300, N ANDOVER, 01845. Meanwhile you can send your letters to 800 TURNPIKE ST STE 300, N ANDOVER, MA, 01845. The company`s registered agent is LEGALINC CORPORATE SERVICES INC. 5237 SUMMERLIN COMMONS STE 400, FT MYERS, FL, 33907. The company`s management are Director, Vice President – Tecce Salvatore, President, Secretary – Youkstetter Karl.

We know from various sources, media etc.  EARTH EXCHANGE   started taking down the building in JANUARY   of 2021

 OCTOBER 30TH 2020

The City of Lorain, Mayor Jack Bradley, Sanford Washington and Max Upton met with Dennis Dannenfelser of Earth Exchange, of the JANUARY 2021 REGISTRATION.

 I HAVE TO WONDER DID WASHINGTON, BRADLEY AND UPTON   ACTUALLY DEAL WITH A REGISTERED COMPANY   AT ALL.

The Chronicle Telegram had in its reporting re the lack of permits is quoted

  All Star Dismantling LLC, out of New Jersey, lists performing the demolition on its website, including drone video footage of some of the work on its website.”

Curiously, ALL STAR DISMANTLING LLC wasn’t a registered company either until APRIL 14-2021 Company Name:

ALL STAR DISMANTLING LLC

Entity Type: DOMESTIC LIMITED LIABILITY COMPANY

File Number: 450635311

Filing State: New Jersey (NJ)

Filing Status: Active

Filing Date: April 14, 2021

Company Age: 7 Months

Registered Agent: Dennis Dannenfelser JR

1249 Oakland Ave

Union, NJ 07083

 

However without benefit of our Law Department a letter was sent out on October 30th 2020  to  Dennis  Dannenfelser highlighting the  fact , Mr. Max Upton  would be  the City  of Lorain  MAIN Contact person

 The Letter of Agreement?

October 30th  2020  Mayor Jack Bradley, Safety  Service Director Washing , Director of Building Planning and Housing and I  am told by  Law Dept. they  were not part of the “agreement” meeting and I  can find no record of our Law Department   even initialing  such  an agreement.

I use the wording “agreement “because that is the wording used by Mayor Bradley in his statement to the media “

There was an agreement that the developer would pull permits one structure at a time, Mayor Jack Bradley said, with plans to level everything but the parking garage.

How do you enter into an agreement with companies that aren’t companies until AFTER the demolition started?

 WHERE WAS THE DUE DILLIGENCE BY BUILDING Housing and Planning Director Upton TO MAKE SURE ALL THE I’S WERE DOTTED AND T’s CROSSED?

  Upton is mentioned in the letter from Safety Service Director Washington as the main contact person for the city therefore, it would have been his JOB OF WORK to follow through.

 

Former St. Joseph Community Center demo on hold after developer fails to pull permits | Chronicle Telegram  May 7th 2021

 The article in the Chronicle Telegram mentioned the lack of permits applied for by the developer However Upton did issue two permits   again those dates and to WHOM they were given – NOT to  Earth  Exchange, Not to  All Star Dismantling LLC  not even to  A7 Development  but TO  South  Shore  Development the PREVIOUS OWNER of the buildings and land.

The first permit DATED MAY 20th  2020  was to  South  Shore Development    nearly  three months AFTER  the site was SOLD to  A7 and work to  be carried out by  Earth  Exchange. (Note the date this was before the October 30th letter of agreement)

 I would also draw your attention to the sloppy work from Building Housing a Planning Chief Inspector at the time . Richard Klinar. The application from Earth Exchange.  Please NOTE – there is NO DATE on the application.

 IF the date and the wrong Company  was given permission “. South  Shore Community  Development Corp”  etc  was incorrectly  added  at the time,  supposedly  due to  software issues, then that too is down to  Upton as he didn’t do due diligence before sending out the permit.

We now come to the 2nd Permit   by  Max Upton  , please note the date on this permit   and also  to which  company  it was issued OCTOBER 30TH  2020 THE DATE OF THE MEETING BUT ONCE AGAIN TO  South  Shore Development Corp   WORK TO  BE DONE BY  Earth  Exchange .

 

This is just another example of lack of due diligence.by Mr. Max Upton and his department.

 We now have the site at the former St Josephs’ Hospital nothing but a pile of rubble and the blame is being laid at the Developer and the City of Lorain is looking for redress. The site is going to have to be cleaned up, litigation is looming.

Photo: Chronicle Telegram Kristen Bauer https://chroniclet.com/news/260993/former-st-joseph-community-center-demo-on-hold-after-developer-fails-to-pull-permits/

I  am not  an attorney  , I  know nothing about LLC’s, Corporations and  their respective responsibilities but I  do  know before entering into  any  business partnership, agreement, giving  permission especially  with   and edifice the size of a whole city  block involving the  City  of Lorain  “all paperwork should be checked and at least initialed by  our Law Dept.” In this particular case since there were concerns of possible toxicity leaching to the ground water through the basements, the EPA should have been included as a safe guard on any such agreement.    That is only common sense, which apparently was also lacking

 

Note I  can find nothing that states  Lorain City  Council Building and Lands Committee , Council At Large  as the Chair of that committee was ever informed of the “agreement” with  these “developers” or “demolition experts”

ON APRIL 24TH MRS, SPRINGOWSKI  SENT MR UPTON AN EMAIL WITH  REGARD TO  THE DEMOLITON OF ST. JOSEPH’S HOSPITAL : AGAIN PLEASE NOTE THE DATES:

From: Springowski, Mary
Sent: Saturday, April 24, 2021 6:17 PM
To: Upton, Max
Subject: Old St.Joseph Hospital

 Did the demolition company bury the concrete from demolishing the old hospital? 

 Someone asked me and I said I had no idea.  Is that permissible,  to bury the debris?

 Mary Springowski 

Lorain City Council at Large 

MR UPTON ANSWERED MRS. SPRINGOWSKI  AND I WOULD DRAW YOUR ATTENTION ONCE AGAIN  TO  THE DATE

 AND WHAT MR. UPTON DIRECTOR OF BUILDING HOUSING AN PLANNING STATED  ON APRIL 26TH 2021

From: “Upton, Max” <Max_Upton@cityoflorain.org>

Date: 4/26/21 1:22 PM (GMT-05:00)

To: “Springowski, Mary” <Mary_springowski@cityoflorain.org>

Subject: RE: Old St. Joseph Hospital

To my knowledge they have not. We are working to make sure the comply with our ordinances.

From: “Springowski, Mary” <Mary_springowski@cityoflorain.org>

Date: 4/26/21 1:32 PM (GMT-05:00)

To: “Upton, Max” <Max_Upton@cityoflorain.org>Subject: RE: Old St.Joseph Hospital

“Neighbors are saying otherwise.”

 Well that is interesting because either Mr. Upton  apparently  had no  clue as to  what was happening a few blocks from Lorain City  Hall and his offices, albeit the demolition had been ongoing for months, covered  with  drone footage , blogs the media  as the walls came tumbling down , scrap taken away  by  the truck load, fences going up.

 

Did  Mr. Upton not have departmental meetings  discuss with  his department and in those  meetings did he not say  ( considering he had a tentative demo schedule,)  AS OF NOVEMBER 2ND 2020  3 days after the meeting with  Dennis  Dannenfelser

Have Permits been pulled, where are we on inspections, have the environmental  licenses been pulled, is there any  toxicity  on the site  the City  of Lorain should know about?

This was a huge undertaking and certainly one would think the checks and balances SHOULD have been in place. Apparently not? More lack of not only follow through by  the Dept. Head  Upton , and certainly   the due diligence was nonexistent!

Mr. Upton had replied to  Mrs. Springowski ‘s question

 Did the demolition company bury the concrete from demolishing the old hospital? 

 Someone asked me and I said I had no idea.  Is that permissible,  to bury the debris?

To my knowledge they have not. We are working to make sure the comply with our ordinances.

Mr Upton apparently lied to  Mrs Springowki in that email dated APRIL 26TH 2021 because  27 days ( almost a month  earlier ) Richard Klinar the Chief Building Inspector  slapped a stop  work order on the site  for the very  issue Mrs. Springowski  was questioning.

MARCH 30 2021 HIS CHIEF BUILDING INSPECTOR SLAPPED  THE SITE WITH  A STOP  WORK ORDER AS THE THE DEBRIS WAS IN THE BASEMENT AND THEY  NEED PERMITS. 

CAN YOU, AS A   IN ALL HONESTY  CONCLUDE THAT MAX UPTON WAS UNAWARE  A MONTH  LATER THIS HAD HAPPENED .

Either he lied to   the Chair of Building and Lands,  Councilwoman  at Large ( who  represents ALL of the citizens of Lorain . Or he was apparently not capable  of follow through  and being the “go  to  guy”. Either way  he should not be heading  the Building Housing and Planning Dept.

 To my knowledge they have not. We are working to make sure the comply with our ordinances.  And Yet the Stop  Work order speaks for itself !

to  be continued:

About thatwoman

It is the principle of the thing! No agendas ( I think? at least I try) I write therefore I am
This entry was posted in City of Lorain, Documentation, Jack Bradley, Lorain Civil Service Commission, Politics and St. Joes, Upton Chronicles and tagged , , , , , , , , , , . Bookmark the permalink.

1 Response to Letter to Lorain Civil Service Commission Pt.2

  1. Pingback: Letter to Lorain Civil Service Commission Pt 3 | OH Her Again!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s